Construction on Pascoag library is under way

March 30, 2011

BURRILLVILLE — Construction work on a $252,000 addition to the town's first and oldest library began three weeks ago and is making rapid progress, according to library officials.
Work on the Pascoag Public Library addition officially began on March 14. As of today, the foundation has been poured and is being finished and walls for the 22-foot by 38-foot addition have been erected.

WOONSOCKET -- Woonsocket Little League’s opening day went off with a hitch Saturday at...
CUMBERLAND — Thanks to second-place finishes in the discus, hammer and 25-pound weight,...
PAWTUCKET – The first time players pick up a bat, they are instructed to swing nice and...
BURRILLVILLE – Residents took time out on a perfect Saturday morning to ensure that their community stayed just as...
NORTH SMITHFIELD – Julia Cloutier, an 18-year-old senior at North Smithfield High School, had a general sense of the...
UXBRIDGE – Voters at the Special Town Meeting on May 12 will be asked to approve a plan to build a new central fire...

 

Premium Drupal Themes by Adaptivethemes